Future Development Highlights
Campus Construction Supports Academic Mission
Advance Academic Excellence
- Advance research agenda
- Reduce documented space deficiencies
- Support new university programs
- Academic V
- Construction Start – 5/07
- Construction Completion – 8/08
- 85,000 square feet
- New facility for College of Visual and Performing Arrs
- Academic VI/Research II
- Construction Start – 6/07
- Construction Completion – 3/09
- 180,000 square feet
- New facility for Volgenau School of Information Technology and Engineering to include academic,
lease and lab areas
- Krasnow Institute Additions
- Construction Start – 1/06
- Construction Completion of current phase – 7/07
- 12,500 square feet
- New lab space
Improve Quality of On-Campus Life
- Continue to invest in on-campus residence halls
- Increase university life and services functions in all capital projects
- Invest in recreation facilities in accordance with athletics master plan
- Parking Deck III
- Construction Start – 9/07
- Construction Completion – 4/09
- Accommodate 1,650 cars
- New Student Housing
- Allow Mason to accommodate approximately 9,000 students
- Northeast Development Project
- Construction Start – 8/05
- Construction Completion – 2010
- 450,000 square feet
- To include retail outlets, fitness center, restaurant, and resident dining facility
- Child Development Center
- Construction Start – 11/06
- Construction Completion – 8/07
- Accommodate 120 children